So I haven’t posted on the blog forever. It has gotten so busy and hectic that I just have not had time to do so. So as you all know. We are having a baby girl in a couple of weeks. We just finished decorating the nursery. It is really girly and turned out super cute. Here are the pics.

Construction has completed on the house. We never thought this day would actually come. We are so happy that we have accomplished this and we are truely proud of our feat. We learned so much in the process and grew a lot. We had our disagreements on things along the way, but it definitely made our marriage stronger.

I was able to take some pictures of the house in it finished state (except final cleanup and paint touchups). The most amazing thing was the carpet. It is the thing that definitely turns it into a home.
We got our carpet from South Valley Floors. It turned out amazing. I really like how it compliments everything. A great finishing touch on our project. Here are the pictures of the different areas of the house.
hpim1352
Upstairs hallway
hpim1350
Great room from kitchen
hpim1349
Great room to front room
hpim1348
Front Room
hpim1343
Great Room
hpim1342
Stairs to upstairs
hpim1339
Master Bedroom
hpim1335
Bedroom
hpim1333
Another Bedroom
hpim1332
Another Bedroom
hpim1331
Great room from upstairs
hpim1351
Stairs
hpim1334
Stairs from above.

So as you can see… the carpet turned out really, really nice.

We also installed the bathroom mirrors within the last few days as well. Here are the pics for those.
hpim1347hpim1346
1/2 bathroom downstairs
hpim1337hpim1336
Hall bathroom upstairs
hpim1341hpim1340
Master Bathroom

They also took the blankets off the concrete, so we get our first full view of the driveway. I have another pic of the walkway to the door but it did not turn out.
hpim1354hpim1330hpim1329

We also got the microwave installed and haven’t had a chance to post it.
hpim1345hpim1344

We thank everyone for following us in our journey and supporting us in the great endeavor that we have done. I am glad that everyone enjoyed the blog and my (Jordon) horrible grammar.
We should hopefully close on the loan within the next week and be in the house by mid-March at the latest. Stay tuned for our future posts about our closing, moving in, home furnishing shopping and upcoming house warming party.

So we have got a quite a bit more done in this last week. Here are the pictures as a result.
hpim1301hpim1300hpim1322
We finally ripped the protective covering on the pantry door to expose the glass door there. It is pretty cool looking.
hpim1293hpim1294hpim1299hpim1297hpim1326hpim1327hpim1298hpim1324
Here are our beautiful appliances. We love them. They definitely bring the kitchen to life. We still have to install the microwave as shown in the last picture. Hopefully that will be done by the electrician on Monday or Tuesday.
hpim1325hpim1323hpim1291hpim1290hpim1285hpim1284
Our door handles on the front door, room doors, and french door.
hpim1302
Kitchen with appliances.
hpim1321
Our 3 light vanities that are in the hall and master bathrooms.
hpim1320hpim1316hpim1315hpim1314hpim1313hpim1311hpim1305hpim1304hpim1303
Plumbing Fixtures
hpim1310hpim1309hpim1308
Here is the sink and the faucet in our half bath. It turned out sooo awesome.
hpim1319hpim1318hpim1317
Here is the plumbing fixtures in our shower. We unfortunately have to return the shower heads because they don’t work with our setup or our water pressure. We are kinda bummed because they are so freakin cool. Hopefully we can find replacements that as cool.
hpim1307hpim1306
Bathroom hardware.
hpim1292
Our doorbell.
hpim1296
Here is a picture of our dog Gomez. Just for fun.

The house should be finished this week.

Monday: Carpet, finishing touches on electrical work.
Tuesday: Carpet if not finished, deck wrapup and install of mirrors.
Wednesday: Final Cleanup
Thursday: Final Inspection (we so so hope), Paint touchups

Hopefully we don’t have too much go awry with the inspection and pass it first time… (haha). But hopefully it is not too bad.

We are almost there and so happy.

We went to the house yesterday and it was very very exciting. The house is soooooo close to being done!!!

hpim1278
Bathroom light in the 1/2 bath… we have POWER!!!!

hpim1277
hpim1276
hpim1270
hpim1269
Light switches, smoke alarms, fan covers and blugs

hpim1275
Better view of our family room fan.
hpim1273
Canned lights above the fireplace.
hpim1274
This is the chandelier above the landing on the stairs.

These are the pictures of cabinets with the countertops installed. The countertop contractor finished everything else up today. All they had left was cutting holes for faucets, and for our vessel sink.
hpim1272hpim1271
Kitchen sink with countertops and cabinets.
hpim1259hpim1258hpim1257hpim1256hpim1254hpim1253
Assorted other pictures of the kitchen in all its splendor.

hpim1267
Half bath vanity. The vessel sink will go here.

hpim1266hpim1265
The vanity in the hall bathroom upstair.

hpim1264hpim1263hpim1262
The laundry room cabinets and countertops and sink.

hpim1261
Master Bathroom vanity with 2 sinks.

hpim1268
The fireplace is fully functional and turns right on with the flip of a switch.

hpim1252hpim12801hpim1279
Here are some photos of the garage doors close and a few different angles. What you see on the far away pictures is the exterior in finished form. You can even see a little bit of the driveway exposed.

We also bought our appliance this weekend at Home Depot.
Here are the links to the ones we selected.
Microwave
Gas Range
Refridgerator
Dishwasher

So we are so very close. Here is a list of the final things that need done.
1. Finish Plumbing (2/10)
2. Carpet (2/12-2/13)
3. Final Cleanup (2/13-2/16)
4. Final Inspection (2/16-2/18)
5. Financing (not sure, hopefully not very long)

We can finally move on! The cabinets have been installed throughout the early part of the week. This was pretty much holding the entire progress of the house. But they are up and they look pretty cool so far.
They still have some finish work to do on them… which is being done on Monday. But the main thing is that the countertop contractor can now measure and template the granite.

Here are the pics taken from this morning.
hpim1247
Kitchen
hpim1245
Laundry Room
hpim1242
More Kitchen Cabinets
hpim1241
In the kitchen where the fridge will go.
hpim1240
Above the stove… when I was there this morning… the cabinets on the left side where not up yet. They should be now.

Here is what is left on the house.
1. Countertops
2. Hardware (doorknobs, cabinets knobs, towel rack, etc)
3. Finish Plumbing
4. Mirrors
5. Carpet
6. Cleanup and touchups
7. Final Inspection stuff (inspection, repairs, re-inspection)
8. Financing
9. Move-in

We are so close we can smell it.

So there was a plethora of items done when I went to the house this morning. It was exciting to see the stuff done. I made the house that much closer to being done.

Here are the pictures
hpim1251hpim1250hpim1249

The deck is pretty much finished… it just need the stairs built off of it. It should be finished soon.

hpim1248
hpim1239
hpim1238

This turned out nice too… It is made of the same material as the deck in the backyard.

hpim1244
hpim1243

Wow… these turned out really nice. I am really impressed by how the shower glass turned out. It looks like it was installed well too. This definitely a homerun.

So overall the work completed this week is going really well. We are sooo close to being done.

The garage doors got installed this morning. They are beautiful. They were ordered and installed by Martin Doors.

We had to go and take pictures of installed so the bank can pay them.

So here are some new pictures that we took yesterday when we went to the lot.  Most of them are for lighting.

hpim1230
This is the light over the dining room table.
hpim1229
Front Room Lights
hpim1228
Vanity in the 1/2 bath… the other bathrooms will have 3 light vanities.
hpim1217
This the ceiling fan in the master bedroom.
hpim1215
These are the ceiling fans that are in the 3 hall bedrooms.
hpim1218
This is the light that is through most of the house. Front room, stairway to the basement, halls, mudroom, master closet.
hpim1214
Ceiling fan in the great room. This isn’t the greatest picture. Will post a better one latter. Our camera ran out of batteries.
hpim1216
5 light chandelier that hangs over the landing of the stairs

Exterior Lights
hpim1227hpim1224hpim1221hpim1219

Air Conditioners
hpim1226hpim1225

This week the following will happen. (Hopefully)

1. The shower glass contractor will come install that in the master bathroom on Wednesday.
2. Cabinets may be installed on Friday… but if they are not, then Monday of next week. (blah) This is holding up a lot of progress on the house. It is really frustrating.
3. Ordering the hardware, having them delivered and potentially having them installed. This depends if the cabinets are finished.
4. Building of steps from garage to interior of house on Tuesday or Wednesday
5. Building of deck in the back yard outside of our kitchen nook door on Tuesday or We
6. Installation of garage doors on Monday
7. Install of water meters.

Once these things are done… all we have left is cabinets, countertops, finish plumbing, carpet, final cleanup, touchups, final inspections and financing.

We have had this sink in our house for a while, but I don’t have any new pictures because we did not make it down to the lot this week. This sink is for our downstairs half bath. We really like this sink. The color is called Speckled Copper. It is a vessel sink, which means it rest above the countertop (ohhhh fancy). We ordered it through http://www.envirobath.com/.

Here is what is suppose to happen this week

1. Finish heating
2. Cabinets (if they get their act together)
3. Garage stairs
4. 8′ x 8′ deck off back of house
5. Prelim countertop stuff
6. Garage doors (hopefully)
7. Shower glass doors
8. finish electrical (switch and plug covers and vanity lights)
9. When cabinets get done… hardware and possibly door knobs

Lets hope this stuff gets done… we are getting really close.

We chose our carpet and carpet contractor… South Valley Floors.

We went out to the lot today to check out the paint job now that it is finished. We really like the colors that we chose out.
hpim1206hpim1204hpim1203hpim1202
This is our front door. We think that it looks awesome.

hpim1198hpim1197hpim1196hpim1191hpim1192
Here is our stairs and railing. It turned out really nice as well. Some of the pictures make it look really light, but it actually shows darker once you are in the house.

hpim1201hpim1200hpim1199hpim1195hpim1190hpim1189hpim1187hpim1185hpim1182
Pictures throughout the house of the paint colors on the trim and walls. We really love this as well. When we were there today we just sat on the fireplace step and stared in awe. We are really happy with our accomplishment. The paint makes it really seems like a real house. One thing that was kinda frustrating was they did not paint the outside of the exterior doors. Not sure what that is all about, but it will be taken care of.

Things happening this week.

1. Finish lighting will be completed this week (stay tuned for pictures)
2. Cabinets will be delivered and installed this week.
3. If we order garage doors on Monday or Tuesday, they may be installed by the end of the week.